Project Overview

Classification Phase 1 (Gangnam~Jeongja) Phase 2 (Jeongja~Gwanggyeo) Phase 3 (Yongsan~Gangnam)
Business title Shinbundang(DX) Line
(Gangnam~Jeongja) private
investment business
Extended Shinbundang(DX) Line
(Jeongja-Gwanggyo) double track
railway private investment
business
Extended Shinbundang(DX) Line
(Yongsan-Gangnam) double track
railway private investment
business
Contents Construction and Operation of
a double Track Railway
connecting city of Gangnam
in Seoul and Bundang
in Gyeonggi-do
Construction and operation of
a Double Track Railway
linking city of Suwon and
Yongin, Bundang in Gyeonggi-do
Construction and Operation of
a double Track Railway
connecting Yongsan and Gangnam
in Seoul
Overview The metropolitan broadband
subway transporation network
privately invested and planned to
provide groundbreaking solution
for traffic congestion caused by
rapid population growth in
southeastern metropolitan area
including Pangyo New Town
The metropolitan broadband
subway transporation network
privately invested and planned to
ensure pulbie transportation to
Gwanggyo New Town development
district, to provide solution for
traffic congestion throughout
Seoul from city of Yong-in,
Suji and northwestern Suwon in
Gyeonggi-do
The metropolitan broadband
subway transporation network
privately invested and planned to
provide solution for traffic
congestion in gangnam, Seoul as
well as improve accessibility
between Seoul and southeastern
metropolitan area
Methods Completed at the same time as the ownership belongs to the state, ensuring operators operation rights
* BTO(Build - Transfer - Operate) method
Section
& Scale
· Gangnam Station, Gangnam-gu
in Seoul ~ Jeongja Station,
  Bundang-gu, Seongnam-si
in Gyeonggi-do Province
· Total Length 18.5km
double-track train
· Project Cost 1.69 trillion KRW
  (May, 2002 based on constant prices)
· Jeongja Station, Bundang-gu,
Seongnam-si in   Gyeonggi-do
Province ~ Gwanggyo station,
  Yeongtong-gu, Suwon-si in
Gyeonggi-do Province
· Total Length 12.8km
double-track train
· Project Cost 1.0255 trillion KRW
  (May, 2006 based on constant prices)
· Yongsan Station, Yongsan-gu
in Seoul ~ Gangnam Station,
  Gangnam-gu in Seoul
· Total Length 7.795km
double-track train
· Project Cost
8,722 billion KRW
  (July, 2007 based on constant prices)
Period Operation period: 30 years after completion
Project
Participation
· Competent Authority :
Ministry of Land,
Infrastructure & Transport
· Concessionaire: Shinbundang
Railroad Co., Ltd.
· Operators: Neo Trans Co., Ltd.
· Competent Authority:
Ministry of Land,
Infrastructure & Transport
· Concessionaire: Gyeonggi
Railroad Co., Ltd.
· Operators : Neo Trans Co., Ltd.
· Competent Authority :
Ministry of Land,
Infrastructure & Transport
· Concessionaire: Newseoul
Railroad Co., Ltd.
· Operators: Neo Trans Co., Ltd.

Project Characteristics

  • DX LINE is

    a mass transit system which is able to provide fundamental solution to
    anticipated traffic southeastern part of the Metropolitan Area and
    Pangyo new town construction.

  • The Metropolitan Railroad

    network construction was led by private investment from planning,
    financing, execution to operation.

  • Gangnam, Seoul and Bundang/Yongin/Suwon, Gyeonggi

    metro system created with cutting-edge technology, which is
    connecting Gangnam area of Seoul and Bundang, Yongin & Suwon
    aims to carry passengers safely and swiftly.

  • It is origin

    of intercity metro network connecting places by the shortest distance.

  • Intercity railroad network connection with the Metropolitan Area metro network

    Transfer to existing Suin¡¤Bundang Line, Subway Line 2, 3, 7, 9 and Gyeonggang Line.
    Connected with other Capital's southwestern lines such as Sinansan Line, Shinbundang(DX) Line extension, etc.

  • The most direct route for fast services

    Reduction of operation time by maintaining average speed of 47.6km/h, Max. driving speed of 90km/h
    Traveling time: 41min 54sec. (based on Gwanggyo-Sinsa train)

  • The shortest route for fast services

    Connecting Seoul's commercial and business center(Gangnam, Sinsa) with southeastern Metropolitan Area
    (Pangyo, Bundang, Yongin, etc)

Expected Effects of DX Line

Time saving(Gwanggyo ~ Sinsa)

½Ã°£´ÜÃà(°­³²~±¤±³) À̹ÌÁö

Economic Effects

  • - Promotion of the first Korean private investment
    projects following Shinbundang(DX) Line
    Project where line planning, construction
    and operation proposal and execution
    were made by private sector
  • - More added value compared to the existing transportation method
  • - Reduction Effect of the number of bus

Metropolitan Area Metro Network

  • - Connection to Gangnam area metro network penetrating eastern and western Seoul
  • - Establishment of a truly astonishing metropolitan area subway network

Suggest a good model for new town
development

  • - Connection Center(Gangnam) and Sub-center(Pangyo, Gwanggyo) in the most effective way
  • - A good model for future sub-central city development

Project Overview

Project Name Private investment for Yongin Light Rail Transit(LRT)
Content Construction and operation of Yongin LRT based on full-automatic driverless system
Project Outline
  • - To effectively cope with rapidly changing traffic demands of Yongin city
  • - To promote balanced city development by providing traffic network service
  • - To build eco-friendly and comfortable city traffic system
Project Details
  • - Ownership: Yongin city
  • - Operating rights: Yongin LRT Co., Ltd (for 30 years after completion)
  • - Operating company: Neo Trans
  • - Operating period: for 30 years after start of operation          [Neo Trans operating and maintaining period(2nd): Aug. 2016~Jul. 2023]
Section & Scale
  • - Total length 18.143km (Giheung~Dongback district~Yongin City~Jeondae/Everland)
  • - Stations: 15
  • - Depot: 1
  • - Vehicles: 30 units(LIM-method)
  • - E&M equipment: Overall
Project Period
  • - Construction: 2005. 12. ~ 2013. 4.
  • - Start of operation: 2013. 4. 26.

Project Characteristics

  • Yongin LRT

    operates using full-automatic driverless system and is a
    cutting edge transportation means focused on safety,
    punctuality and environment

  • By promoting balanced development
    of Yongin city¡¯s east¡¤west areas,

    And also by connecting with GSMA
    (Great Seoul Metropolitan Area) subway lines, Yongin LRT enables its
    passengers to quickly enter places like Seoul and is therefore a future-oriented city rail that would boost potential values of Yongin

  • From waterside parks to trails,

    Wherever Yongin LRT runs, urban parks, trails, waterscape facilities,
    brooks and fountains are installed. LRT runs with nature all together

  • Passengers¡¯ safety

    Is the utmost priority. Neo Trans is putting its best effort for
    the sake of customers¡¯ safety and convenience by
    introducing and installing rail trespassing prevention device,
    safety fence, silent warning system, and wheelchair spaces
    and elevators for the disabled.

Expected Effects of Yongin LRT

Suitable effects for city environment

- Excellent punctuality, safety and eco-friendliness

Á¤½Ã¼º, ¾ÈÀü¼º, ģȯ°æ¼º

Middle scale of transport capacity between bus and subway

- Bus: less than 5,000 peopleSubway: less than 30,000~80,000 people

¹ö½º, °æÀüö, ÁöÇÏö

Construction cost reduction

- 50% cut down on cost per km compared to that of subways

1000¾ï 500¾ï

Management cost reduction

- Fully automated driverless system(40~50% of personnel required compared to that of ordinary subways)